Electrical & Plumbing Upgrades — Step-by-Step SOW

Purpose: Replace outdated/unsafe electrical and plumbing systems so the building meets current code, supports Phase-2 program needs (kitchen, laundry, fitness center, clinic, daycare, computer lab), and provides safe, reliable infrastructure for residents and staff.

High-level combined timeline: 6–10 weeks (tasks overlap; final timing depends on building size, permitting, and contractor availability).

Pre-Work (Assessment + Permits) — (1–2 weeks)

  1. Site survey & system inventory

    • Licensed electrician and licensed plumber perform detailed walkthroughs; document existing panels, wiring, conduit, fixtures, water/service piping, drains, hot water systems, backflow devices, and risers.

    • Inspect for asbestos/lead/hidden hazards before cutting/penetrations; if present, coordinate abatement first.

    • Deliverable: Existing Conditions Report with photos and recommended replacement scope.

  2. Design & engineering

    • Prepare electrical one-line diagrams, load calculations, panel schedules, and plumbing riser diagrams. Include lighting layout, emergency lighting, and kitchen/laundry equipment power needs.

    • Provide drawings for permit submittal and contractor bidding.

    • Deliverable: Permit-ready drawings and specifications.

  3. Permitting & coordination

    • Submit plans to local building/electrical/plumbing inspectorates; obtain permits.

    • Coordinate shutdown windows with Owner and other trades (mold/lead work, roof, HVAC).

    • Deliverable: Permit approvals and scheduled inspection windows.

Task A — Electrical Upgrades (major steps & rough timeline: 4–6 weeks)

  1. Power shut-down planning & safety

    • Develop lockout/tagout and temporary power plan (phased if necessary). Notify occupants and post signage.

    • Deliverable: Shutdown plan.

  2. Demolition / removal of unsafe systems

    • Remove unsafe knob-and-tube, undersized circuits, damaged panels, exposed splices, and obsolete conduit. Carefully cut and cap conductors per code.

    • Deliverable: Demolition log & photos.

  3. Service / Meter / Main Panel

    • Upgrade service capacity if required by load calc (e.g., replace service entrance, meter base, main breaker, or add new service).

    • Install or reconfigure main distribution panel(s) and required subpanels with appropriately sized breakers and clear labeling.

    • Deliverable: New main/subpanel installation; one-line diagram updated.

  4. Branch circuits & conduit

    • Install new branch circuits sized for kitchen equipment, laundry, fitness center, clinic, computer lab (dedicated circuits for ovens, commercial washers, treadmills, server/IT equipment). Use code-compliant conduit and cable types.

    • Add AFCI/GFCI protection where required (kitchen, bathroom, daycare, exterior).

    • Deliverable: Circuit schedule and as-built wiring map.

  5. Lighting & controls

    • Rewire lighting circuits; install LED fixtures, emergency egress lighting and exit signs on emergency circuits, occupancy sensors where appropriate, and centralized lighting controls as specified.

    • Prepare for Phase 2 drop-ceiling and LED retrofit (coordinate layout with ceiling heights).

    • Deliverable: Lighting punch list and energy-report (if requested).

  6. Life safety & low voltage

    • Install/upgrade fire alarm panel/interconnects and smoke/CO detectors as required by code. Wire and test emergency lighting and exit pathways.

    • Install or prepare pathways for data/voice (CAT6) and security system (camera/power/PoE) for Phase 2 security buildout.

    • Deliverable: Fire alarm test report, low-voltage pathway layout.

  7. Grounding & bonding

    • Ensure proper grounding electrode system, grounding conductors, and bonding for gas/water/metal piping. Perform continuity and resistance tests.

    • Deliverable: Ground test results.

  8. Testing & commissioning

    • Perform insulation resistance (megger) tests, polarity and continuity tests, breaker coordination/load testing, and verify GFCI/AFCI operation. Conduct load testing on major equipment circuits.

    • Schedule and pass electrical inspections with authority having jurisdiction (AHJ).

    • Deliverable: Test reports and inspection approvals.

Electrical Acceptance Criteria

  • New service and panels installed per plan and accepted by AHJ.

  • All circuits labeled, grounded, and protected; GFCI/AFCI functioning.

  • Emergency lighting & exit signs operational on backup/emergency circuit.

  • Documentation: as-built one-line, panel schedules, test results, warranty info, and O&M manuals delivered.

Task B — Plumbing Upgrades (major steps & rough timeline: 5–7 weeks)

  1. Shutoff & isolation planning

    • Plan domestic water shutdowns and temporary water provisions; notify Owner.

    • Deliverable: Water shutdown plan.

  2. Remove & replace damaged water piping

    • Replace corroded or inadequate supply piping (galvanized to copper/PEX/approved material). Replace sections as needed from mains to fixtures. Install metering and backflow prevention as required by code.

    • Deliverable: Piping replacement log and material submittals.

  3. Drainage & sanitary upgrades

    • Replace/repair damaged soil stacks, waste lines, venting; confirm slope to drain and proper trap installations. Install or replace floor drains, grease trap for kitchen per local health codes, and sewage ejectors where required.

    • Deliverable: Sanitary riser diagrams and slope verification.

  4. Hot water system

    • Replace or install commercial hot water system sized for kitchen, laundry, clinic (tank or tankless, with recirculation pump if required). Install expansion tanks and appropriate temperature/pressure relief valves.

    • Deliverable: Hot water system specs and startup report.

  5. Fixtures, ADA & water efficiency

    • Replace fixtures (toilets, sinks, showers) with ADA-compliant and water-efficient models where specified. Install commercial laundry hookups and laundry room plumbing for Phase 2.

    • Deliverable: Fixture schedule and installation photos.

  6. Gas piping (if applicable)

    • Inspect and, if needed, upgrade gas piping for kitchen equipment; perform leak tests and regulator/valve checks. Coordinate with gas utility if service upgrades needed.

    • Deliverable: Gas pressure test certificates.

  7. Testing & commissioning

    • Conduct hydrostatic pressure tests for supply piping, air or water testing for waste/vent systems per code, verify hot water temps and recirculation operation, and perform trap priming and flow tests for fixtures and drains.

    • Schedule and pass plumbing inspections with AHJ.

    • Deliverable: Hydrostatic & waste test reports, inspection approvals.

Plumbing Acceptance Criteria

  • No leaks under static and operational testing.

  • Hot water at fixtures within acceptable timeframe and temp settings per code/owner spec.

  • Backflow preventer installed and certified, grease trap installed per health code.

  • Documentation: as-built risers, fixture schedules, test reports, warranties, and O&M manuals.

Combined Sequencing & Coordination Notes

  • Coordinate with lead/mold abatement: Perform hazardous-material abatement prior to opening walls/ceilings. If abatement occurs concurrently, use containment and negative-pressure zones.

  • Electrical rough-in and plumbing rough-in should be scheduled after demolition but before new insulation/gypsum board. Inspections for rough-in must be passed prior to concealment.

  • HVAC and roof work may need to precede some electrical/plumbing finish work (e.g., rooftop unit power and condensate drains).

  • Temporary systems: Provide temporary power/water where necessary to maintain basic operations.

  • Phased occupancy: If some areas remain occupied, establish strict isolation, PPE, and safe egress paths.

Safety, Codes & Qualifications

  • All work by licensed electricians and master plumbers with commercial experience.

  • Contractors must carry General Liability, Workers’ Comp, and Pollution coverage where required; provide certificates.

  • Work must comply with NEC, local electrical code, International Plumbing Code (or local), and AHJ requirements.

  • Use lockout/tagout, confined space procedures (if applicable), and respirators when working near abatement zones.

Deliverables (to require in proposals)

  1. Permit-ready drawings and signed permits.

  2. Daily logs & photo documentation.

  3. As-built drawings (electrical one-line & plumbing risers).

  4. Panel schedules and circuit labeling.

  5. Test reports (megger, ground, hydrostatic, gas pressure).

  6. Inspection sign-offs from AHJ.

  7. Warranties and O&M manuals.

  8. Final commissioning checklist and owner walkthrough sign-off.

Testing & Acceptance Checklist (for final acceptance)

  • Electric: Service voltage correct, insulation resistance pass, AFCI/GFCI functional, all breakers/trip settings verified, emergency lighting & exit signs tested, AHJ sign-off.

  • Plumbing: Supply pressure stable, no leaks, drain flows within expected rates, hot water system delivers required temps, backflow preventer certified, AHJ sign-off.

  • Documentation: As-built drawings, test results, and manuals submitted and approved by Owner.

Timeline Summary

  • Pre-work (surveys, design, permits): 1–2 weeks (parallel)

  • Demolition & hazardous checks: 1 week

  • Electrical rough-in & panel work: weeks 2–5

  • Plumbing rough-in & drain work: weeks 2–6

  • Inspections (rough-in): end of week 4–6 (as scheduled)

  • Finish wiring, lighting, fixtures, hot water commissioning: weeks 6–8

  • Final testing, commissioning, AHJ inspections & sign-offs: weeks 8–10
    (Adjust for building size and permit scheduling.)

Cost Guidance (high level)

  • Costs vary by scope, local labor rates, and required service upgrades. Require detailed line-item bids for: demolition, materials (panels, breakers, conduit, piping, fixtures), labor, inspections, testing, and contingency for unknowns (old wiring, concealed rot, asbestos).

  • Recommend 3 competitive bids and hold a pre-bid walkthrough.

Contractor Selection Checklist

  • State license numbers for electrical and plumbing.

  • Evidence of commercial experience (projects similar size/type).

  • Proof of insurance and bondability.

  • Provide schedule, staged shutdown plan, and list of sub-contractors.

  • Include manufacturer warranties and maintenance training for staff.

  • Provide references and past AHJ inspection pass records.

Quick SOW Sentence

“Contractor shall perform electrical and plumbing upgrades in accordance with the provided design drawings and applicable codes; work includes service/panel upgrades, new branch circuits and lighting, fire alarm/egress wiring, replacement of domestic water and sanitary systems, hot water system installation, testing, third-party inspections, and delivery of as-built drawings and test reports prior to final acceptance.”

Previous
Previous

Floor Removal (Damaged Section)

Next
Next

HVAC Safety Upgrades